At nearly 6m wide and 5m high, the 14-tonne stainless steel tank that rolled out of DTS Engineering in Normanby made for an impressive sight on the road to Taupō.
The tank was designed and built by DTS to hold almost 100,000 litres of sulphuric acid, for use in cleaning pipes and various tanks in a geothermal power plant. It’s made from stainless-steel, with a 16mm base and walls that taper up to 8mm at the top. The tank is fully insulated and includes automation to hold the acid at a stable operating temperature.
It is a key component of a turn-key project being completed by Dialog Fitzroy for a large Geothermal electricity generator.
“DTS have been building stainless-steel tanks for dairy farms for 40 years,” says chief executive Gavin Thwaites. “The key skills and experience of our engineering team were easily transferred to deliver this key project to the customer’s expectations within the project timelines.”
With highly corrosive acid in the tank, it’s the steel that’s at risk. The 316-grade stainless steel is not reactive with sulphuric acid above 98% concentration, but corrosion accelerates sharply below that threshold, so the build quality was critical.
And while DTS have been diversifying into the food processing, beverage and pharmaceutical industries for a few years, Gavin sees winning the tender from Dialog Fitzroy as a landmark.
“Dialog Fitzroy are recognised nationally and internationally for innovative engineering solutions. We’re known for dairy tanks. Being able to deliver this component of their critical infrastructure is a big deal, but even more important is the opportunity to show we’re ready to collaborate with others in the sector to help them deliver for their clients.”
Adrian van’t Hof, project manager for Dialog Fitzroy, agrees collaboration will be critical to Taranaki maintaining its leadership in engineering capability and capacity in a changing supplier environment. “We work directly with customers, without a consultant in the middle. The workload ahead for the sector is huge. We don’t want to be limited just by our own capacity.”
Gavin sees investment in people and technology as critical to being able to meet the needs of a more diverse customer base, as well as the increasing demands of the country’s dairy sector.
“We have upskilled our team to meet engineering standards for these larger projects. We have six apprentices among our team of 35, and we’re continually investing in our people, and our tools, alongside our commitment to LEAN manufacturing processes that reduce waste across our processes.”
“There’s no question in my mind that the ability to work together will be what it takes to keep Taranaki at the forefront of engineering in New Zealand.”
Photo: South Taranaki’s DTS Engineering has built a large tank for a geothermal electricity project in Taupō as it looks to diversify its work.